Friday, February 15, 2008

the end of the week


where we are at as of friday feb. 15. incredible in my mind. this is going up so fast with just 4 of us.

Tuesday, February 12, 2008

2 more days of hard work


Manuel arrived yesterday. he is a local man. hes 64 years old and will help us out for around 4 hours a day. he is a great cob mixer. he just lost his job sweeping the street of our neighborhood, the new mayor fired everyone and hired all his friends

Saturday, February 9, 2008

later in the day

if you look at the photo below this one you will see (above) what we accomplished in about 6 hours, three of us working.

Friday, February 8, 2008

The foundation and stem wall are done. Floor levels are compacted and leveled and are about 1.5" below final grade. The Cob walls started going up on 2 days ago

Saturday, February 2, 2008

tamping the dirt in the bags

bag stand


above photo: this is gordon upon completion of the bag stand with the bag in place. ready to fill with dirt

Wednesday, January 30, 2008

more work


even gabriel gets in on the action.

working on the stem wall


a more comprehensive picture of what we are doing. this is a ton of work

gordon


gordon fry, from northern california. he has been here for the last 2 weeks or so. he is resting on the earthbag stemwall. these bags are sitting on ground level, right over the rubble trench. they are rice bags, filled with the same dirt excavated from the trench, mixed with 10% cement to stabilize the dirt and 20% water, then filled the bags, fold the bags shut and tamped into place. to lock the bags together on the horizontal surface we laid 2 rows of barbed wire to stop them from shifting.

ollie


olliver adams, "ollie" from london, he has been here for the last week or so. he is sitting above the rock "keys" to lock the stem wall to the future cob wall

sauna foundation

above photo is gabriel helping digging out the sauna foundation. this is made from cement bricks with lime/cement/sand morter. i did this to have smaller walls, for both the sauna and toilet area. for the rest of the house i used earthbag foundation.

you can see my first mistake here. i did not dig out the subfloor first. i then had to do it carefully when the stemwalls were there

filling the rubble trench

above photo is the foundation excavation. inside is a long piece filter fabric that is covering a three pieces of 2" inside diameter black tube made from HDPE, i drilled 1/2" holes into the tube almost everywhere to let rainwater flow through and out of the foundation

above photo is me filling the trench with large stones. i then covered this with small stones to the top

harvesting


collecting/harvesting stones by the creekside to fill the rubble trench for foundation drainage